LV Switchboard and Generator Transfer: Define the Interface

Low-Voltage Switchgear Guides

Published 2026-09-07 | Updated 2026-09-07

Published by Jinxing Electric. This buyer guide supports specification discussions; confirm the final configuration and document scope for your project.

Low-Voltage Switchgear for project specification review

Short Answer

Before ordering an LV switchboard with generator transfer, agree which supplier owns the switching devices, transfer logic, generator commands and protection settings. Most interface problems arise when each package is individually specified but the combined operating sequence is left undefined. A signed interface schedule should accompany the single-line diagram.

Get a Project-Specific Recommendation

Send your single-line diagram, voltage, capacity or feeder schedule, destination country, quantity, and required standard. Jinxing will review the closest product configuration and return the missing technical questions before quotation.

Send Project Requirements

Before ordering an LV switchboard with generator transfer, agree which supplier owns the switching devices, transfer logic, generator commands and protection settings. Most interface problems arise when each package is individually specified but the combined operating sequence is left undefined. A signed interface schedule should accompany the single-line diagram.

Decide what the transfer must achieve

A standby generator serving selected essential loads has a different duty from a system intended to transfer an entire facility. Identify the loads that must remain supplied, the interruption they can tolerate and the loads that should be disconnected before transfer. Include large motors and loads that may restart together.

State whether the intended arrangement permits any overlap between sources. Closed-transition or parallel operation requires appropriate engineering and utility approval; it must not be assumed from an “automatic transfer” description. IEC 60947-6-1:2026 is the current IEC publication for transfer switching equipment, but citing it alone does not define a site's complete source-management scheme. Its published scope excludes certain arrangements, including bus-tie and multi-source transfer equipment. Have the designer identify the applicable equipment and assembly requirements for the proposed system.

Draw the package boundary

The switchboard supplier may provide an integrated transfer arrangement, while the generator supplier provides a controller and starting system. A controls contractor may add supervisory monitoring. Allocate every signal and power supply between these parties before fabrication.

InterfaceDetail to agreeTypical owner to identify
Generator start requestContact or communications command and status feedbackTransfer-controller and generator suppliers
Source availabilityVoltage/frequency assessment and failure indicationSystem designer and controller supplier
Breaker or switch operationMechanism supply, status contacts and command permissionsSwitchboard supplier
Neutral arrangementSwitching decision and earthing relationshipElectrical installation designer
Load sheddingWhich feeders disconnect and when they may returnPlant controls designer
Alarm reportingSignal list, destination and acknowledgementControls integrator

Example: essential loads are smaller than the normal load

Consider an illustrative factory with a generator intended to support lighting, controls and one process line, while the normal LV board serves several production areas. A quotation for an incomer transfer arrangement may be electrically plausible but incomplete if all outgoing feeders automatically reconnect to the generator.

The project must define an essential-load section or a deliberate load-shedding sequence. The switchboard order should include the required feeder interfaces and feedback points. The generator package should be reviewed against the resulting load steps. Neither supplier should be asked to discover the intended operating limit during commissioning.

Resolve neutral and protection questions early

Changing between sources can change the fault-current conditions and the relationship between neutral and earth. Ask the responsible designer to specify the neutral arrangement and evaluate protection coordination under both utility and generator supply. Do not select a three-pole or four-pole arrangement from a cabinet model name.

The review should identify which settings, sensing connections and control supplies apply in each source condition. Document how the installation responds when an auxiliary supply is unavailable. A transfer sequence that works during a normal demonstration may behave differently after a prolonged outage or a failed battery charger.

Specify acceptance scenarios, not just component brands

Ask for a functional test schedule covering source loss, unsuccessful generator availability, restoration of the preferred source, failed switch position feedback and local/remote selection. These are acceptance scenarios for the supplier's documented procedure, not instructions for field switching.

Agree who witnesses the integrated test and who records the controller settings. Where factory testing cannot include the actual generator, list the simulated interfaces and the remaining site tests. This prevents a successful panel-only test being presented as complete system validation.

Issue one coordinated RFQ package

Send the LV switchboard supplier the source diagram, essential-load schedule, proposed generator information and interface matrix. Require a clear list of inclusions, exclusions and assumptions. The preferred offer is the one whose scope closes the transfer interfaces and can be verified, rather than the one that simply lists two incoming switches and an automatic controller.

References

Product Family and Related Guides

FAQ

1. Is an automatic transfer controller enough to define the switchboard?

No. The source arrangement, neutral design, control supplies, load shedding and interfaces must also be agreed.

2. Who decides whether the neutral is switched?

The responsible installation designer should make that decision from the earthing and source arrangement, then specify it to both suppliers.