RMU Transformer Feeder Configuration Guide

Ring Main Unit Guides

Published 2026-06-28 | Updated 2026-09-06

Published by Jinxing Electric. This buyer guide supports specification discussions; confirm the final configuration and document scope for your project.

Jinxing ring main unit for medium-voltage loop networks

Short Answer

Configure an RMU by naming each cable and transformer function on the single-line diagram, defining normal switching states and checking both ring through-current and individual transformer duty. Function count alone does not describe an equivalent assembly.

Get a Project-Specific Recommendation

Send your single-line diagram, voltage, capacity or feeder schedule, destination country, quantity, and required standard. Jinxing will review the closest product configuration and return the missing technical questions before quotation.

Send Project Requirements

Translate the network into named functions

A request for a “three-way RMU” leaves several questions unanswered. Three ways can serve different combinations of cable connections, transformer branches and switching duties. Suppliers also use different letters to identify their functions, so a short configuration code should always be accompanied by a legend and single-line diagram.

Name each circuit by destination. Identify the ring cable from the previous station, the cable to the next station and each transformer branch. Then state which devices perform normal switching, isolation, earthing and fault interruption. A label such as “incoming” does not prove that the circuit includes a fault-interrupting device.

Build a function schedule

FunctionOperating informationRating or interface to review
Ring cable ANormal state and alternative feeding directionThrough-current, cable termination and switching duty
Ring cable BOpen-point responsibility and restoration roleTransfer loading and the approved earthing arrangement
Transformer branchTransformer identity and protection boundaryPrimary load current, fault duty and coordination inputs
Metering functionExact energy or voltage measurement pointInstrument-transformer configuration and space
Reserved functionInstalled spare or future additionReal primary interface and available enclosure arrangement

Keep the topology decision separate from the review of load switching and fault-interruption duties. A switch-fuse arrangement also requires coordinated fuse selection; these protection decisions cannot replace a complete function schedule.

Distinguish transformer current from ring current

For an illustrative 1,000 kVA three-phase transformer at 11 kV, rated primary current is approximately 52.5 A, using I = S / (√3 × V). This calculation describes the transformer branch at its stated rating.

The ring cable ways may carry additional downstream stations, especially after a network reconfiguration. They must be assessed using the relevant network load flow, rather than the local transformer's current. Conversely, a cable way's current rating does not establish the required protection behavior of the transformer feeder.

These numbers are an example only, not a statement of a Jinxing model's available ratings or a recommended protective setting.

Write the normal and contingency states

A ring-shaped cable route can be operated with an open point. Document where that point lies and which organization controls it. Also describe permitted restoration states after a cable section is isolated. Closing a ring or connecting two sources may change fault levels and protection requirements; it cannot be assumed permissible because two cable ways exist.

A practical review scenario is a station normally fed from cable A, then temporarily fed from cable B. Ask whether the transformer protection remains selective and whether the metering boundary still measures the intended circuit. The project engineer should resolve those operating assumptions before the equipment configuration is finalized.

Check the assembled arrangement

Request the order of functions, cable entry positions, operating access and secondary compartment needs on one arrangement drawing. Where a metering function or spare branch is added, reconfirm the complete dimensions and the relevant verification evidence. Avoid assuming that another unit's function code implies identical construction.

For an RFQ, provide the network diagram, function schedule, transformer data, minimum and maximum source fault levels, earthing arrangement and approved operating states. Start with ring main units and send the documents through project enquiries. Availability, insulation technology and the final assembled configuration require a specific proposal; component descriptions do not imply separate supply.

References

FAQ

1. Is a three-way RMU always two ring switches and one transformer feeder?

That is a possible arrangement, but the function code and each circuit's duty must be defined on the offered single-line diagram.

2. Can the local transformer current determine every RMU way's rating?

No. Ring cable ways may carry downstream loads and contingency transfers that are larger than the local transformer branch current.