Switchgear Interlocking: Build a Reviewable Cause-and-Effect Schedule

Medium Voltage Switchgear Guides

Published 2026-09-07 | Updated 2026-09-07

Published by Jinxing Electric. This buyer guide supports specification discussions; confirm the final configuration and document scope for your project.

KYN28-12 Metal-Clad Switchgear

Short Answer

A switchgear interlocking schedule should identify each controlled action, its required conditions, the implementing mechanism and the expected response when a condition is missing. Local, remote and cross-panel commands need a coordinated review.

Get a Project-Specific Recommendation

Send your single-line diagram, voltage, capacity or feeder schedule, destination country, quantity, and required standard. Jinxing will review the closest product configuration and return the missing technical questions before quotation.

Send Project Requirements

Quick answer

Request a cause-and-effect schedule for the offered switchgear. It should connect each permitted or blocked action to named signals, mechanical provisions, key systems or control logic, with an agreed acceptance method. The phrase “standard interlocks included” does not describe the project's complete operating philosophy.

Separate equipment interlocks from site logic

Some interlocks are built into a specific equipment mechanism. Others depend on adjacent panels, transformer arrangements, utility conditions or the owner's control system. Treat these as distinct responsibilities so that a factory provision is not mistaken for a complete site-wide scheme.

For example, Schneider Electric's Masterclad manual describes mechanical provisions associated with breaker position and racking, while identifying certain key interlocks as specified options. This illustrates why the actual product manual and order configuration matter; it does not establish the provisions of another manufacturer's panel. Masterclad interlock descriptions.

Make each requirement testable

Use one row per requirement and assign stable identifiers. The examples below describe review questions, not an approved operating sequence or a complete protection scheme.

Requirement identifierAction or interfaceInformation to defineEvidence to request
IL-01Local closing commandRequired equipment states and permissivesMechanism description and control drawing
IL-02Remote closing commandLocal/remote selection and approved command conditionsLogic diagram and point mapping
IL-03Cross-panel relationshipSource, destination and state of each permissiveInterpanel wiring or key schedule
IL-04Loss of an input or supplyRequired blocked state, alarm and recovery behaviourAgreed failure-response test case
IL-05Maintenance-related accessApplicable equipment provisions and authorised methodManufacturer instructions and project review

Include the approving engineer and drawing revision for each row. Distinguish a requirement that is accepted from one that merely appears in a supplier's proposed logic.

Resolve ambiguous states before programming

A signal labelled “ready” can hide several assumptions. Identify the actual source, normal state, validity condition and what happens when the input is unavailable. For remote commands, record where the permissive is evaluated and how rejection is reported to the operator.

Mechanical provisions, electrical circuits and software logic also have different dependencies. Ask which functions remain effective when communications or auxiliary power is unavailable. The answer must follow the actual equipment and approved system design; avoid generic promises of fail-safe behaviour.

Example: local review misses a remote path

Consider a hypothetical installation where the factory drawings describe local controls, while a separate integrator develops remote commands. Both teams assume the other has implemented a cross-panel permissive. The individual panels can pass isolated checks while the combined logic remains undefined.

The buyer can expose that gap by requiring a common IL-03 row showing the originating device, transmission path, receiving logic and expected response. The factory test can verify the agreed internal portion, and a site integration test can verify the external interface. Each test then has a clear boundary and owner.

Preserve the schedule through acceptance

The acceptance plan should cover both permitted and blocked commands under the approved test conditions. Qualified personnel should use manufacturer-approved methods; procurement documents should never invite bypassing interlocks to demonstrate a function.

Any drawing or software revision that changes a condition should update the schedule and its affected test cases. Retain the final version with the operating documentation so that future modifications can be reviewed against a known baseline.

Information for a switchgear enquiry

For medium-voltage switchgear configurations, provide the single-line diagram, operating philosophy, local and remote command requirements, and existing interpanel interfaces.

Use the project enquiry page to request the proposed cause-and-effect schedule with the KYN28-12 panel or other suitable configuration. Final interlocking provisions and applicable documentation need technical confirmation for the project.

References

FAQ

1. Are standard panel interlocks enough for a multi-panel scheme?

Not necessarily. Cross-panel, utility and remote-control relationships need a coordinated project schedule in addition to the equipment-specific provisions.

2. Should remote commands appear in the same schedule as local commands?

Yes. Identify their separate paths and shared conditions so that the factory and control-system integrator can agree ownership and acceptance tests.